Skip to main content

Excluding developers who miss sprint planning

Last post 04:48 pm February 15, 2016 by Andrzej Zińczuk
6 replies
07:17 am October 1, 2015

Shall a developer who missed the sprint planning be allowed work on that sprint's increment?

Concrete case is that developers vacation ended a two days after sprint 10 planning. As Scrum Master I advised him to rejoin the developer team only in Sprint 11, as for Sprint 10 he could not:

- hear the Product Owners presentation of the top product backlog items
- contribute to the decision on what can be done in the Sprint
- contribute to the discussion how the chosen work will get done
- agree to the Sprint Goal

Scrum Guide does not explicitly mention this case. So what would you think?


07:06 am October 2, 2015

It is the Development Team as a whole which forecasts the work that can be achieved during the Sprint, not the individual developers. If the Dev Team can confidently make a forecast including the developer who's on vacation (knowing how he works), then they should do so, and the developer should pick up work on his return.


01:32 pm October 2, 2015

The Development Team should self-organize to allow for each others' absence, including vacations. Note that a Scrum Master should beware of giving advice that might be interpreted as a command-and-control decision.


01:48 pm October 2, 2015

+1 to what Ian Mitchell said.

Also, have you considered the implications of 'firing' someone for 1 sprint because they missed sprint planning? Any idea what that will do to morale?


04:15 am October 5, 2015

Team member absence's can be schedule, or not. What if someone get sick one day or has to go to a funeral or has a car crash ?

It could be a good experiment to observe what append when a member is missing the Sprint Planniung Meeting.


05:01 pm October 7, 2015

Thanks a lot for your valuable input. Let me answer Tim's and Olivier's above questions, as I did the "experiment" in a development team of 4 (sprint length 3 weeks):

- The developer was surprised to be excluded from the sprint
- He used the time to fully process his pile of work after 2 weeks vacation (e-mails etc.)
- He did an online-training and did work on some other products
- He attended the daily scrums and backlog grooming meetings
- He improved unit-test coverage of the product
- The Sprint completed successfully (velocity went down, but not 25%)
- Morale was and is still good - we are still friends

Anyway, next time I would include a developer who is not available the first few days in a sprint.


04:48 pm February 15, 2016

every time you decide instead of team, you are risking having self-organization not to emerge


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.