HI -

I just sat the PSM I and came across a question related to Sprint 0 - a concept that doesn't feature in 'The Definitive Guide to Scrum: The Rules of the Game'.

Is Sprint 0 a recognized concept for the purposes of the PSM I test?

Thanks

S


08:18 am June 30, 2014

No, it isn't. See these threads for more information:

https://www.scrum.org/Forums/aft/645
https://www.scrum.org/Forums/aft/366


02:54 am July 1, 2014

From SCRUM timeboxed events perspective, it is not a valid sprint. It is usually the name given to do initial activities like refining product backlog, architecture envisioning, priortization and release planning etc.


12:05 pm July 2, 2014

Yes it is if you are using Zero-based numbering like in C like language.

If you are using VB then it starts with 1.


05:00 am July 3, 2014

> From SCRUM timeboxed events perspective,
> it is not a valid sprint. It is usually the name
> given to do initial activities like refining
> product backlog, architecture envisioning,
> priortization and release planning etc.

True. However just to be clear, it isn't the nature of these activities which make the "Sprint Zero" concept invalid. The problem is that it does not usually result in an increment which the Product Owner values, nor is it usually timeboxed for that purpose.

It could be argued that a PO *should* value the things you mention, and that readying the Scrum instance is a meaningful goal for the first sprint.


04:37 pm July 7, 2014


From official scrum guide - there is no Sprint 0.

In practical world, when a team sets out to adopt Scrum - usually Sprint 0 is used for the first time to adopt the scrum framework in the current business process.

Sprint 0 - as any other sprint - has a goal. The goal usually is to set the team for a change. The goal is agreed by the scrum team. One of the basic requirement of the scrum is to have a product backlog and this sprint 0 is ideal to solidify the approach to maintain the backlog either in Agile software tools/Wiki or shared project notebook or post it notes on the wall. or select another that simplifies the work.

Sprint 0 - may or may not have a potentially ship-able product increment - agreed by the scrum team.

http://www.mountaingoatsoftware.com/blog/sprint-zero-a-good-idea-or-not


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.