Development KPIs and Scrum? Is there any useful KPI that can be applied within/across scrum teams?

Last post 05:44 pm December 6, 2013 by Joshua Partogi
4 replies
11:16 am December 4, 2013

Hi,

Generally I was looking information about KPIs in Scrum. Not because I need them by myself. This is an organization idea. I don't see a point for making it but I may be wrong.
Do you use any KPIs in Scrum teams related to development in Scrum teams? If yes what are they?
If you don’t see a point, what are your arguments for it?


12:12 pm December 4, 2013

Who is asking for these KPI's? The Product Owner...or project/program managers who are trying to cut themselves into the Scrum deal?

In agile practice the only measure of success is the incremental delivery of working product. If your organization is looking for KPI's, it implies that this either isn't happening or it isn't seen as being enough. If so, why not? Why accept indicators in place of actual value? KPI's are the devil's work, because they subvert the idea of what value is and who consumes it.

Of course, there are *metrics* which Scrum Teams might choose to provide to a wider audience, such as:

- delivery metrics, e.g. whether or not increments are being delivered and Sprint Goals are being met.
- agile transformation metrics, e.g. those furnished by Agility Path


12:17 pm December 4, 2013

Hi Andrzej,
here is my experience with this.
We communicated the velocity (User Story Points per sprint) regularly.
Management made a KPI of it, because it was the only number they got from us.
As Pressure from management increased to rise the velocity, the quality decreased.
What we did as a reaction was
1) Helping management to understand this phenomenon
2) Adding metrics for quality.
They include:
Number of bugs resolved
Checkstyle warnings (only high)
Findbugs warnings (all)
Number of branches not covered by tests

PMD warnings are planned.

The visibility of these metrics is enough to encourage the developers to improve them.
In addition we included rules for these metrics (except number of bugs) in the Definition of Done.

Hope I could help here.
Best, Ludwig


12:43 am December 5, 2013

The only KPI I think I care about is the ROI of the product. What metric is better than that?

Keep in mind that the "return" or "value" of a product can be defined by an org in any way. Yes, if they define it poorly then they will have a KPI that may not work well. Having said that, if they poorly define value or return, then they have much bigger problems than tracking metrics.


05:44 pm December 6, 2013

IMHO profit generated per Sprint is the best metric because people can not game it.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.