About to the "Set the Sprint Goal"

Last post 02:35 pm May 17, 2017 by Ian Mitchell
1 reply
08:42 am May 17, 2017

Hi All,

I have a question about the "Sprint Goal".



Normally Scrum Team crafts a Sprint Goal at the Sprint planning.

But following sentence confused to me;

"Having set the Sprint Goal and selected the Product Backlog items for the Sprint, the Development Team decides how it will build this functionality into a “Done” product Increment during the Sprint."

is "set" wording mean used to like "assigned"?

2016-Scrum Guide US Page-9 / Topic Two

 

Thanks for helps,

 


02:35 pm May 17, 2017

It's more a matter of having agreed the Sprint Goal, such that the team view it as a shared commitment for the Sprint upon which they can subsequently focus.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.