How to use sprints with kanban for scrum teams (PSK) ?

Last post 08:02 pm February 29, 2024 by Ian Mitchell
2 replies
12:58 am February 29, 2024

I need help with a Kanban concept for scrum teams (PSK).

In the Scrum Guide it is written that we must start a sprint immediately after finishing the previous one.
In the Kanban Guide for Scrum Teams it says that in the definition of Workflow we can/should consider steps before and after the sprint (Upstrem for example).

My question is: How will the team start a sprint immediately when the other finishes, given that I have steps before and after the sprint in my workflow?

Sorry if my English isn't adequate, it's not my main language.


07:40 pm February 29, 2024

A good, concrete example is refinement. Before a Product Backlog Item is pulled into a Sprint, it needs to be refined by the team. Any steps that are part of your refinement process may very well be represented as steps in your Workflow, where your team can focus on work in a particular state at Sprint Planning.

Another example may be an integration effort. If your Scrum Team is a software development team working on a system, the next step after a Product Backlog Item is Done could involve a systems integration team that integrates the Done software with hardware built by another team.

Neither of these scenarios has any bearing on when Sprints begin and end, but there is work that happens before a Product Backlog Item is pulled into a Sprint and work that happens after the Product Backlog Item meets the Scrum Team's Definition of Done that you may want to represent on a Workflow, especially if you want to measure something like lead time before it ends up in the hands of a user.

 


08:02 pm February 29, 2024

My question is: How will the team start a sprint immediately when the other finishes, given that I have steps before and after the sprint in my workflow?

Because those steps may occur in other Sprints, outwith the commitment point for creating Done work that meets a Sprint Goal. 


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.