Hi,

Can we say that the sprint backlog is created during the sprint? I know, it's created during the sprint planning, but after all, the sprint backlog emerges during the sprint.

So it's also right to say the sprint backlog is created during the sprint...?

 


09:27 am March 7, 2017

There is a difference between the Creation and Emergence.

BTW why do we want to justify it and to whom?


09:57 am March 7, 2017

The output of the sprint planning is sprint goal and sprint backlog items. The SB items are then decomposed to a list of tasks per item.

for example:

if the SB is "extract the customer information into a csv format and send mail"

then this item is decomposed to a list of tasks like

1. Write a sql query to extract the information.

2. Save it in csv on database server

3. Attach the extract and send mail to the concerned party

now the DT starts work on these tasks, later they have identifies that for doing the third task they need to write a shell script to pick the file up and then send.

so they break the task 3 into further like

write a shell script to send an email

automate this whole process if its needed on periodcal basis using a cron job

 

so as you see the sprint backlog emerges during the sprint.

 

thanks

manikanth


03:20 pm March 7, 2017

> Can we say that the sprint backlog is created during the sprint?

The Sprint Backlog ought to be created and burned down in the Sprint.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.