There is a lot of confusion around sprint backlog. As per my understanding it is owned by the development team and they can modify the sprint backlog. Can somebody help explaning who can replace the sprint backlog items? Also about sprint backlog items, task, work?


04:31 pm February 21, 2017

Development team


02:41 pm February 23, 2017

Only the development team best knows how to tackle sprint backlog items and decompose them further into tasks. If they are lost then they can take help of the product owner and as well as the stakeholders to clarify their questions through out the sprint. 

Short answer is "The development team"


07:17 am February 24, 2017

The Sprint Backlog is the Development Team's forecast of the work they need to do to meet the Sprint Goal. The Goal was agreed with the Product Owner during Sprint Planning and cannot be changed. The Sprint Backlog is wholly owned by the Development Team and they can replan it as they see fit to better achieve the Goal, including replacing items.

If any selected Product Backlog Items are replaced then the PO ought to be consulted in order to confirm that the agreed Goal does indeed remain unaffected. This collaboration also allows the PO to revise the Product Backlog as necessary and to appraise stakeholders.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.