Can a Scrum team can change sprint length in case they don't have much item in the backlog / not aware about the priority.

Last post 05:14 pm July 8, 2022 by Ian Mitchell
1 reply
04:49 am July 8, 2022

I am a scrum master and handeling one cross functional team which has already delivered its first phase of MVP which client have asked. 

Now team have very limited amount of backlog item in which priority has set by the PO. 

PO did not have received feedback from the client about the next phase of work or priority.

In this situation to keep the work going on can the Team change the sprint length? 

 

Thanks in advance for your advice. 

Bhavik.


05:14 pm July 8, 2022

Right now you're not Sprinting at all, because there's no empirical feedback at the end of each timebox. Without that feedback to inform the Product Owner about how value is being optimized, it's unsurprising that the Product Backlog has become starved.

The issue isn't a matter of Sprint length. It's a matter of work being conducted in phases which are not Sprints at all. That's the problem to solve.

 


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.