Cycle time, can't wrap my brain around it

Last post 06:21 pm June 22, 2022 by Chuck Suscheck
7 replies
12:29 pm June 16, 2022

Per PSK,

Cycle time metrics are always given with finished work in a percent of time as I understand it.

If I have a 3 devs, and we complete our work 80% of the time in 6 days how exactly do you use that information to better the team?   Is it even beneficial to try to forecast with cycle time or is it strictly to be used in retro to try to improve.

If I have 100 stories left to complete on a team with  3 team members and 80% of the time we finish work in 6 days or less, how would you calculate that forecast or is it too incomplete of a picture?

Thanks for any help understanding this.


12:47 pm June 16, 2022

If I have a 3 devs, and we complete our work 80% of the time in 6 days how exactly do you use that information to better the team?   Is it even beneficial to try to forecast with cycle time or is it strictly to be used in retro to try to improve.

Your team is trying to meet a Sprint Goal, and an understanding of cycle time could prove invaluable to their plans for key backlog items. When should we start them, with a reasonable expectation of their being finished?

Bear in mind that improving cycle time could actually be a Sprint Goal itself.


01:48 pm June 16, 2022

what I am struggling with is the math to produce that "reasonable expectation" in that scenario.

If we finish our work 80% of the time in 6 days or less but there are 100 items left to complete the feature how does one come up with that reasonable expectation.

 

Or in a sprint goal scenario lets say we have 10 items to finish to meet the sprint goal and we finish our work 80% of the time in 6 days or less... 



6 days x 10stories  - 60 days?   / 3 devs = 20 days there is a 80% chance we will be completed?     Is that kind of the sprit of it?


02:29 pm June 16, 2022

I am about the worst arithmetician in the world but yes, that is the spirit of it. I suspect the wisest approach however may involve the running of simulations using collected historical data.

I wrote a couple of blog posts on such matters:

https://www.scrum.org/resources/blog/monte-carlo-forecasting-scrum

https://www.scrum.org/resources/blog/flow-optimization-sprint-boundary

 


03:16 pm June 16, 2022

I think you are asking about probabilistic forecasting, which uses a range and a probability. You can use your data and mote carlo simulation to forecast a Sprint and a release. 

Here is an additional blog explaining it: https://www.scrum.org/resources/blog/create-faster-and-more-accurate-forecasts-using-probabilities


06:02 pm June 16, 2022

I'm with @Ian on being bad at math.  However, these books by Daniel S. Vacanti really helped me understand how to use metrics like Cycle Time for forecasting.  

  • Actionable agile metrics for Predictability
  • When will it be done?

 


01:43 pm June 20, 2022

Thanks everyone

 

At some point I hoping to get the actionable agile plug in to help me do these forecasts and monte carlo sims.


06:21 pm June 22, 2022

Focused objective (the company) has some free spreadsheets to look at.

Cycle time and the related scatter chart is for 1 item (the next thing coming in will be complete in 8 days or less 80% of the time.

When you look at groups of items or over a time period, now you need some sort of simulation - that's monte carlo.

It's like saying - there is a 70% chance of the next person walking in this room is going to be under 6 foot tall.  That's cycle.  Asking "what's the chance of the next 10 people walking in the room being under 6 foot tall - that's where the simulation comes in.

It took me a while to get this under my hat also.  


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.