Hi All
Do we need to have 2 separate sprint planning meeting of 4 hours each or 1 meeting of 8 hours?
Who decides this ?
And what could be the factors for choosing either of them?

Thanks
----Abhijit


05:33 am May 26, 2014

Hi Abhijit,
in the updated Scrum Guide from 2013, there is only one Sprint Planning meeting which is 8 hours for a 4-week sprint.
The reason is that some teams, (instead of taking the PBIs into the Sprint Backlog first and breaking them down afterwards as in the previous version) take the first PBI, break it down, take the next one etc. until they think they have enough. The advantage is that they gain a deeper understanding of the work to be done, so they can make a better estimate how much they can get done.
The team decides this, because it is self organizing.


07:02 am May 26, 2014

An important thing to bear in mind is the crafting of the Sprint Goal. Suppose you spent time breaking down each selected PBI before deciding on the Goal. Would that be more or less efficient than identifying a suitable goal prior to this decomposition? Either situation might be the case.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.