Skip to main content

Scrum Master and knowing statuses

Last post 03:28 pm May 9, 2022 by VD Tran
3 replies
06:59 pm May 5, 2022

Hello Community,

I need some advice on a unique situation I am going through. My organization is asking scrum master to provide weekly status of features. They want me to present how features are going and if things are according to the timeline. I could definitely pass that along after having communicated with the product owner and the architectural lead. However, they are asking me questions like "How does pushing a certain functionality to production affect the end clients?" AND "What is being done about UAT testing? Were the end clients provided with a test script for usability testing? What is being done when they don't have access to log in?".

Additionally, I m being asked if end clients are able to use the product  or what value they are getting if the team completes certain user stories. We have the VP of product, director of delivery and product managers in the call. 

When I spoke with my manager who is the IT developers director, she is telling me that the organization has always had scrum masters know the status and timeline. They are the ones who know the "how". And the product owners provide the "what" and "why".  How am I provide these statuses when I am being asked all these architecture/ product heavy related questions? Thank you!


08:01 pm May 5, 2022

the organization has always had scrum masters know the status and timeline. They are the ones who know the "how". 

I'd suggest that isn't good enough. The organization should be more ambitious and have Scrum Masters focus on improving its understanding of Scrum, and how it can better leverage empiricism under conditions of high uncertainty.

For example

  • Never mind status reports. Establish transparency so those doing the work can inspect and adapt based on what they see.
  • Respect the Developers as the technical experts who know how their own work is being Done
  • Respect the Product Owner as the accountable authority who understands the progress of incremental value delivery over a given timeline

Perhaps management are thinking of a Scrum Master as being yet another manager in their own mold: someone who co-ordinates, orchestrates, and directs. If so, that's one of the very assumptions which may need challenging.


08:18 pm May 5, 2022

It sounds like your organization doesn't understand the role of the Scrum Master. Instead of considering the Scrum Master to be a coach and a facilitator, they are looking at the role as something closer to a project or program manager.

From a purely coaching perspective, if key stakeholders are asking about the status and progress of development work, I would be looking toward the information they need and the information radiators that the team is providing. I'd approach it from two fronts. Toward the stakeholders, I'd want to make sure that they understand agility and iterative and incremental development and how to best interact with teams working in this way, including what measures and metrics make sense to address their concerns. Toward the team, I'd look for ways to make the work and state of work highly visible and reduce the manual burden of updating information, trying to integrate it as seamlessly as possible into the team's way of working.

The questions that your organization are asking you are things that others should be able to answer, either the Product Owner or one or more of the Developers. Having the Scrum Master serve as a funnel for communication is not only missing the purpose of the role, but will only add a bottleneck to the process.


03:28 pm May 9, 2022

"How does pushing a certain functionality to production affect the end clients?"

 

Can you ask them why they ask you this question insteaf of the product owner?


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.