PO Backlog

Last post 02:23 pm November 1, 2019 by Tony Divel
4 replies
12:15 pm March 9, 2014

Hi there
Just a question on backlog and whether dependencies are taken into account by the PO ) goes against the Independent part of Invest) or would these be prompted by the Dev Team.

Is priority a no go term now since the Scrum guide talks about an ordered list ?

Thanks
Kb


01:08 pm March 9, 2014

By definition any dependencies between user stories must mean they are not independent. Since dependencies can arise in both business and technical contexts, it follows that both the Product Owner and Development Team have a part to play in identifying them. This is one of the reasons why Product Backlog refinement should involve the whole Scrum Team.

It's fine to consider Product Backlog items in terms of priority. The important thing is not to confuse priority with order, because they are not necessarily the same thing. Lower priority items can rank above higher ones if they allow a more coherent Sprint Goal to be crafted, or if they allow important contingency to be be planned into high-risk sprints. In such cases priority may be expressed not in terms of an item's order but rather in terms of its value (e.g. MoSCoW priority), and any given sprint may contain a mix of differently valued items.


02:06 pm March 9, 2014

Thanks Ian


01:28 pm November 1, 2019

Hi,

is it possible to use moscow in user stories itself?

To prioritize some requirements of a user story?

 


02:23 pm November 1, 2019

It could be an interesting exercise for teams who are struggling to keep acceptance criteria simple and valuable. I'd imagine any requirement classified as 'will not have' should probably be struck from the user story. 

This approach could create significant overhead if you're doing it for every story. I've typically found it more useful for the story itself, however, that's not to say you can't give it a try and inspect whether it's worth the time to get that granular. 

You could also try a liberating structure called 'Min Specs' to help teams get down to what they really need to achieve the goal. 

http://www.liberatingstructures.com/14-min-specs/


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.