Hello,
I am prepping for SM cert. and getting started with burndowns. What do you make of the one below?
Assumptions/ scenarios based on my current knowledge:
- The team is doing fine, they have been working on bigger tasks and waiting for QA - day 9 & 10; (unit & integration?)
- The team is having some impediments blocking their progress - defect, dependency; dropping 12 tasks on day 9, testing and delivering before the x-mas party
Analysis and recommendations appreciated.
Thankful for all your feedback.
First, you post has nothing for us to look at for analysis.
Second, burn-down charts are not mentioned anywhere in the Scrum Guide. So if you are encountering questions about burn-down chart analysis in your prep material, I'd start questioning the validity of that material.
While a large population uses burn-down charts, it is going to be difficult for anyone to give you feedback without more information provided.
Can there really be a burndown of work at all, if nothing is Done and completed until Day 10 at the earliest? If so, what is that burndown showing?