Product Backlog Item's estimates?

Last post 04:39 am June 9, 2020 by Ian Mitchell
10 replies
06:44 am November 27, 2013

I got a little doubt over Product Backlog Item's estimates. I read somewhere that the DT is responsible for all the estmations but the PB items are created by the PO and Product Backlog items have the attributes of a description, order, estimate and value.
So who create the estimations for PBI:
(1) PO discussing with DT
(2) DT only
5) DT along with PO after understanding the PBI


08:46 am November 27, 2013

None of those options. Responsibility for making estimates lies wholly with the DT but only after discussing the PBI with the PO.


04:42 am March 10, 2014

In page 13 of scrum guide: "The Development Team is responsible for all estimates. The Product Owner may influence the Development Team by helping it understand and select trade-offs, but the people who will perform the work make the final estimate."
So I think "2. DT only" is correct option.


12:22 am March 11, 2014

From what I understand the PBI's are given an estimation in story points during product backlog grooming and sprint planning sessions. These are just an estimate of size. The DT will then create tasks for each selected PBI and these tasks will then get time based estimates.


05:28 pm March 17, 2014


Posted By Justin on 11 Mar 2014 12:22 AM
From what I understand the PBI's are given an estimation in story points during product backlog grooming and sprint planning sessions. These are just an estimate of size. The DT will then create tasks for each selected PBI and these tasks will then get time based estimates.


When estimate PBI's during the Sprint Planning the PO can't use the estimation as input to order the Product Backlog. I read that the DT can use 10% of time for refinement and estimate the Backlog.


05:38 pm March 17, 2014

I have a related question.

We have two development teams and one product backlog. What’s best practice for refinement and estimate the backlog? Is it possible that team A do the refinement and estimation of a few PBI’s and that team B put these PBI’s on their Sprint Backlog?

When that’s possible than in my opinion it’s also possible that refinement and estimation is done by a part of the development team instead of the whole team. But I understand that is not recommended.


05:26 am March 19, 2014


Posted By Franck van der Sluijs on 17 Mar 2014 05:28 PM


Posted By Justin on 11 Mar 2014 12:22 AM
From what I understand the PBI's are given an estimation in story points during product backlog grooming and sprint planning sessions. These are just an estimate of size. The DT will then create tasks for each selected PBI and these tasks will then get time based estimates.


When estimate PBI's during the Sprint Planning the PO can't use the estimation as input to order the Product Backlog. I read that the DT can use 10% of time for refinement and estimate the Backlog.



Correct. The backlog will be ordered in terms of value by the PO. The DT will then choose which tasks to put into the Sprint Backlog, considering the PO's priority order. The DT will try and do as many of the top items it can fit into the sprint, but can select lower priority items if they need to fill a small gap in the sprint backlog.


12:45 am February 28, 2019

Product Backlog items have the attributes of?

A、Description

B、Order

C、Estimate

D、Value


09:56 am November 23, 2019

Product Backlog items have the attributes of?

A、Description

B、Order

C、Estimate

D、Value

All of this is correct answer


02:21 pm June 6, 2020

Hello Ian Mitchell,

What about value points? (similarly to story points)

i think that PO is the only one responsible for making that estimate. 

i think that DT is responsible for all estimations only for items that are selected to be executed during a sprint, including effort and size estimations. 

I appreciate your valuable feedback. 

Regards!


04:39 am June 9, 2020

The purpose of estimation is to help a team to get its arms around how much work it can take on.

The assessment of value, which is a different measure, ought to be made by the Product Owner, perhaps in consultation with stakeholders.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.