Last post 12:28 am November 2, 2013 by Sushilkumar Pandey
6 replies
07:58 am October 29, 2013

I would appreciate, if some one could please answer , whether it is correct to say that the development team conforms to the Definition of Done in a scrum methodology.



08:27 am October 29, 2013

It would be more correct to say that the work actioned by a Development Team must conform with the team's Definition of Done in order for the associated increment to be considered release-ready.


08:29 am October 29, 2013

DoD is created by a collaborative effort of the Scrum Team including the Development Team. Scrum Team owns the DoD


08:32 am October 29, 2013

The quote from the Scrum Guide:

"Although this varies significantly per Scrum Team, members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the definition of “Done” for the Scrum Team and is used to assess when work is complete on the product Increment"


08:59 am October 29, 2013

> Scrum Team owns the DoD

I agree, but we need to be careful here. When forming a Definition of Done, the Scrum Guide says a team must consider the "conventions, standards, or guidelines of the development organization". Also, "If there are multiple Scrum Teams working on the system or product release, the developer teams on all of the Scrum Teams must mutually define the definition of 'Done'."

I interpret this as follows. A Scrum Team will wholly own its Definition of Done, but that does not obviate its duty of care towards the organizational attainment of consistent release quality.


11:36 pm October 29, 2013

The Definition of Done evolves as the team evolves in its Scrum journey. In other words as a team matures it can introduce more stringent criteria into its Definition of Done.

For eg. A Build verification test might become mandatory once a team has a well defined environment to execute the tests. Then the DoD can be extended to include this test as well.

In humorous terms if a team completes a feature which meets the team's DoD it can go on a vacation provided the PO comes along


12:28 am November 2, 2013

Thanks All,

From the discussion above , I interpret Scrum team conforms the Definition of Done


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.