The Scrum 30 days or less is Calendar 30 days, or Net 30 days

Last post 04:18 am January 26, 2022 by Saneaki Oshikoji
4 replies
06:55 pm January 25, 2022

For the purpose of development and QA planning, we are setting only 20 net days for the maximum length for The Scrum, because the calendar 30 days include weekends and holidays in different countries.  30 days minus 9 days (average 4 to 5 Saturdays and Sundays) minus 1 day (average national holiday in one month) = 20 days.  By case by case, we reduce it to 15 days.

Any project plan exclude the holidays in addition to the weekends as non-working days.  So, I understand that the Scrum 30 days maximum duration rule means "Maximum Net 20 days".

Is my understanding correct?  Please let me know of your thoughts.

Regards,

Sam


08:54 pm January 25, 2022

The Scrum Guide says that Sprints "are fixed length events of one month or less". A more sophisticated interpretation is unlikely to prove helpful.


10:53 pm January 25, 2022

I've never needed anything better than "one month or less".  As @Ian Mitchell said, I don't see where trying to get as exact as you are is really worth doing. 


01:02 am January 26, 2022

In addition to what the others mentioned, complex product development comes with a lot of uncertainty and many unknowns. Most likely things will change during the Sprint and new learnings will emerge. As the saying goes, plans are worthless, planning is everything. Those of us who have worked with Scrum long enough have become comfortable with uncertainty, and see Developers replanning every day for the next 24 hours.

By the way planning a Sprint for a month, compared to shorter Sprints, isn't forbidden but does adds an extra challenge.

All the best!

 

 


02:18 am January 26, 2022

Thanks for all of your comments.  As conclusion, the Scrum doesn't specify any more than 30 days maximum, neither it includes or excludes non-working days.  However, it doesn't improve the efficiency to be so precise, but the effort shall be spent for day-to-day planning stage as complexity and uncertainty are the big variables.  Certainly, it is just a framework.  I can leave as is how we are operating now.

Regards,


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.