New Item in Sprint Backlog

Last post 04:04 am September 24, 2013 by Ian Mitchell
1 reply
03:39 am September 24, 2013

Hi

Wanted to know, if i identify new item in between of Sprint.
Do i directly add it in Spint Backlog, or do i need to discuss it in daily scrum and add once it got approved in daily scrum ( But in that case i am not stick with the purpose of daily scrum) or do we need to discuss it with Product Owner and need to be add in Product Backlog.

Please suggest.

Thanks


04:04 am September 24, 2013

If the new item is a requirement that expresses business value, then you should discuss it with the Product Owner. The PO owns the Product Backlog. He or she can then decide whether or not to include it, and if so how it should be ordered. However, the Development Team will be responsible for gauging or estimating its size.

If the new item is a task - something you need to do to complete a requirement and meet the Sprint Goal - then you need to discuss it with the rest of the Development Team. You don't have to wait until the Daily Scrum to do that, you can hold that discussion at any time. The Development Team can then plan the task into the Sprint Backlog. That's a team activity.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.