Burndown Chart

Last post 09:46 am September 20, 2013 by Christoffer Kappers
4 replies
05:55 am September 19, 2013

Hi,

is the burn down chart required to measure the time in sprints or is it ok to have the time in days as wel?

/Christoffer


06:57 am September 19, 2013

Product burndown is usually tracked in sprints (e.g. story points completed per sprint).

Sprint burndown is normally tracked in days (e.g. task hours completed per day).


07:14 am September 19, 2013

Burndown is not required at all. It is just a tool to visualize progress in the sprint. The team can choose whatever method they want as long as they inspect the progress toward the sprint goal. Personally I prefer the sprint burndown to show completed stories or story points and not tasks, since we're delivering stories and not tasks.

If you're talking about release burndown I don't see the difference between days and sprints. All sprints have the same length and the next sprint starts as soon as the previous ends, but maybe I got the question wrong.


02:17 pm September 19, 2013

While the Sprint Burndown is no longer required per se, monitoring sprint progress in some fashion is still required, and it is still required to sum the amount of work remaining in the sprint on a daily basis.

Most teams use a sprint burndown for this purpose, and while you don't have to use a sprint burndown, you do *have to use something.*

What units you use is flexible. Some teams use ideal hours, real hours, ideal days, story points, the "number of tasks", number of acceptance tests, etc. IME, most teams use something like ideal hours or ideal days, with the more advanced ones doing "micro-stories" and burning down in story points.

More about micro stories here:
http://www.scrumcrazy.com/User+Story+Pattern+-+Micro+Stories


09:46 am September 20, 2013

Hi,

it makes sence like you wrote Ian that there is a product burndown tracked in sprints and a sprint burndown tracked in days.

I read somewhere that the burndown should be tracked in sprints and i thought that they meant this was regarding the sprint burndown, however i think it was meant like you explained Ian.

Thanks the replies!


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.