Skip to main content

What Scrum Master should do if we are in last week of planned Release and Developer goes on unplanned leave?

Last post 08:19 am November 16, 2021 by Niall Fallon
6 replies
11:46 am November 15, 2021

12:06 pm November 15, 2021

What do you believe the SM should do in such a situation? 

In my view, the Developers in the scrum team should be cross functional and self-managing, so they should decide via consensus if they still have enough capacity to achieve the sprint goal or not, in order to see if they need to start negotiations with the PO or to approach you if they see having one less developer as an impediment. 


01:18 pm November 15, 2021

What do you mean by "last week of planned Release"? Is the Sprint Goal in jeopardy because of one Developer's absence?

The unit of planning and execution in Scrum is the Sprint. At least once per Sprint, the team should produce an Increment that is potentially releasable. A team should always have a working product got a release on a fixed date. The only question would be scope - is the full set of intended features available.

If the team is encountering a situation where they cannot meet their Sprint Goal, they should work with the Product Owner to maximize the value of the work that they do accomplish and ensure that the Sprint results in at least one potentially releasable product. The Scrum Master may be asked to facilitate these efforts.


05:53 pm November 15, 2021

Impact on release due to unavailability of 1 developer ? if release preparation is strict responsibility of only that developer, then that is not what Scrum recommends in a team. a SM should help the team to visualise this problem and guide them to find a solution to avoid such Bottleneck situations.


06:32 pm November 15, 2021

What Scrum Master should do if we are in last week of planned Release and Developer goes on unplanned leave?

Aren't the team planning to release work every Sprint? They should be. If they are, can the Sprint Goal still be met and a Done increment created? What contingency did the team plan into the Sprint to allow risks like this to be managed and controlled?


06:52 pm November 15, 2021

What Scrum Master should do if we are in last week of planned Release and Developer goes on unplanned leave?

My answer is that the Scrum Master has nothing to do here but observe how the Developers self-manage their reaction to accomplish the work.  Then discuss the challenge with the team during a Sprint Retrospective to see if they felt there is anything that they need to do deal with this type of situation in the future.  


08:19 am November 16, 2021

1 developer should not make that much of a difference, if they do then it suggests that you have a Silo or maybe the team is taking on too much.

Reduce scope, replan the sprint. Inform the PO of the reduction, suggest to the PO that the stakeholders will need to be informed.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.