Workshop technique for estimating large work items (collection of User Stories) for project planning

Last post 07:42 pm March 19, 2021 by Laurent VIDAL
9 replies
03:16 pm March 17, 2021

I'm looking for a workshop technique on how to estimate features/themes/epics, or any large collection of User Stories without estimating each story itself.

Let's start with that we develop a large Scrum project for a client. Now we are in the unfortunate situation where there is a fixed deadline and the C-Level of the client expects a certain feature set to be available until the release. Gut feeling says the scope is too much so we want to provide an estimate of what could be ready until the release and what might be developed afterwards. This information would be necessary for them to arrange the market communication accordingly.

A prioritized list of these high level features exists. We typically do estimations using Planning Poker based on User Stories but I assume this will not work out on a higher level.

  • Did you facilitate a workshop to estimate this high level work 6 month into the future?
  • What method/technique did you use?
  • How much detail should go into the description of the single items? They can not be discussed as in the Backlog Refinement.

My current idea: Affinity Estimation where the reference bucket size would be something in the scope of half a sprint.

I'm open for suggestions.

 


04:02 pm March 17, 2021

Have you had a look at what Liberating Structures has to offer?


04:13 pm March 17, 2021

Let's start with that we develop a large Scrum project for a client. Now we are in the unfortunate situation where there is a fixed deadline and the C-Level of the client expects a certain feature set to be available until the release.

Can you clarify why Scrum is being used for this, exactly? What purpose are Sprints expected to serve?


04:57 pm March 17, 2021

@Scott: I got through the list of routines recently to find a way to spread information so that it is understood not only heard. I'll definitely have a look at them again. However, I see them more as methods for problem solving. Can you point to two or three you would see as a setup for an estimation meeting?

@Ian: Scrum is used since it is the framework the dev team and whole company is most familiar with. Sprints are more or less used to gather feedback of the current state of the application and changing features accordingly. On the other hand there is still a high amount of (user validated) Must features. These are the ones we should estimate to adapt the roadmap and give a better answer as to: This will make it into the release, these are still unclear and those will be definitely coming afterwards.


05:16 pm March 17, 2021

Sprints are more or less used to gather feedback of the current state of the application and changing features accordingly. 

How is feedback being obtained? It doesn't sound as though the client is receiving product value iteratively and incrementally, so that evidence-based forecasts can be made.


06:11 pm March 17, 2021

1-2-4-ALL seems like a good choice, but so do the options listed on the link you provided.


09:53 pm March 17, 2021

Fixed scope, budget, and timelines didn't work in waterfall and it doesn't work in Scrum. You cannot fix all three sides of the iron triangle. You can have a fixed 6-month date, just make sure you are transparent that the scope cannot be fixed. You can certainly be transparent in Sprint Review with regards to progress.

If you have any empirical data as to how much work your team completes in a Sprint you can look into using Monte Carlo forecasting. Again, there are no guarantees, but it can provide a forecast and likehood for completion.

 


01:03 am March 18, 2021

Hello @Thorsten,

Sometimes we use "Affinity Estimation" or "Magic estimation" to provide an overview for stakeholders. As Chris said, there are no guarantees.

Here we are using a combination of "magic estimation" and "rate of error". This rate is calculated by the difference between previous estimation "magic" with the real estimation "planning poker". So you need to get the magic estimation and use same user story in planning poker to "calibrate" the rate. Then you can use it to provide a forecast with the range of deadline.

Usually we get the job done within the deadline range. Some projects close to the best scenario some projects close to the worst.

**Important to remember,  agile projects take advantage from changes. In my option, try as much as you can to avoid set deadlines because we tend to follow the agreement  even though the agreement doesn't make sense.


12:39 pm March 19, 2021

Thank you all. I now prepared the workshop as Affinity Estimation. This should give us a good understanding of the work ahead.

As a forecast I now dug deeper into Monte Carlo. This is a great tool to communicate in possibilities which I much more appreciate than just use Yesterday's Weather.

We do know that the current situation has anti patterns regarding scrum and agile working. We are in the process of inspecting how we got here, what are the symptoms and what cause them, so that we know how/what to change to get back on track.


02:15 pm March 19, 2021

If there is a a compulsory need for estimation, that is compulsory from management and you can't fight it for now,

one solution could be to use extreme quotation.

https://www.myagilepartner.com/blog/index.php/2019/05/14/extreme-quotat…

It is collaborative, with deleveloppers. You could have a rough idea, to begin to work with.

But before doing it you have also to see if management will not blame Developpers to hold on the estimations.

This is the most used trap.

 


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.