Hi all,

I'm struggling to understand how we can apply story-point estimated strategy for cross-functional team which probably includes BAs, QCs, Devs

Will we split the estimate based on their specialized skill and sum up finally? E.g: Testing : 2points, Dev: 3 points. Total = 5 points

Or every team member will estimate individually for a whole story despite the fact their expertise are different?

Please give me the advice


11:36 am May 16, 2020

Which approach would most enhance collaboration, and shared ownership of the work involved?


02:15 am May 17, 2020

Are you required by management to assign points so that they can run reports on performance and amount of work completed?

If so, ask the Development Team members to come to consensus, or the Scrum Master helps bring them to consensus. You don't want to waste time differentiating between a 3 and a 5. It's all a forecast.

If not, why assign points at all. Ask the Development Teams members for how many Product Backlog Items they can complete in a Sprint. They select from the most refined items and convert what they select into a releasable increment.


11:19 am May 18, 2020

I'm struggling to understand how we can apply story-point estimated strategy for cross-functional team which probably includes BAs, QCs, Devs

How about whole team estimates and at the end reach to consensus ? Will this foster collaboration and shared understanding of the PBI ? 


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.