Unfinished story carry forward to next sprint

Last post 04:15 pm April 28, 2020 by Steve Matthew
2 replies
06:32 am April 28, 2020

By the end of sprint, we always have story half way in development or SIT, and have to be carry forward to next sprint.

A few observations:

1. Many of our story need more than 1 sprint (2 week sprint) to complete. 

Is that a must to size the story so it can be complete within 1 sprint? 

2. We often start our story in mid / end of the sprint, knowing that will not be able to finish within the sprint.

How can we complete all stories just right within a sprint? There're always a few days capacity left by end of the sprint to pick up a few new stories.

Appreciate some advice here.


03:22 pm April 28, 2020

What have you committed to? Are you able to meet your agreed Sprint Goal, and to deliver an increment of release quality work?


04:15 pm April 28, 2020

By the end of sprint, we always have story half way in development or SIT, and have to be carry forward to next sprint.

A few observations:

1. Many of our story need more than 1 sprint (2 week sprint) to complete. 

Is that a must to size the story so it can be complete within 1 sprint? 

 

@Adriana Tung, The purpose of a Sprint is to create a Done Increment that is potentially releasable. Having said that have you along with your team been able to identify why you are not able to complete work within a Sprint? Are there any dependencies? Assume you have the ability to make changes, what changes do you think could help you complete them in within your Sprint timebox?

 

2. We often start our story in mid / end of the sprint, knowing that will not be able to finish within the sprint.

How can we complete all stories just right within a sprint? There're always a few days capacity left by end of the sprint to pick up a few new stories.

 

I hope my previous response helps answer the first half of the question. For the second half, if you have capacity to take on a few more stories, nothing is stopping you from doing so. As long as the Sprint Goal is not endangered (i.e. you must be able to meet your Sprint Goal) you can take on additional work if you have the capacity.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.