Product increment as input of the Sprint Planning

Last post 11:26 am February 19, 2020 by Ian Mitchell
3 replies
07:15 pm February 17, 2020

The Scrum guide says about the Sprint Planning "The input to this meeting is the Product Backlog, the latest product Increment, projected capacity of the Development Team during the Sprint, and past performance of the Development Team "

What is the main reason for the latest product increment to be an entry?


10:07 pm February 17, 2020

A product is developed incrementally.

There should be a "Done", releasable increment of the product. The Development Team should be able to inspect and adapt towards producing at least the next increment within the new sprint.

Without transparency about the most recent increment, how could a Development Team forecast what can be included in the next increment?


11:31 pm February 17, 2020

In addition to what Simon Mayer said, I can also think of an example to consider.

What do you do when you change your Definition of Done? Work that was previously done and incorporated into the Product Increment may not meet this definition. The team needs to consider the current state of the product to help guide their planning. Depending on the nature of these changes, the fact that some work is "undone" may cause the team to need to slow down, either to be more careful or to invest time and bring the work up to the current Definition of Done.

This is similar in nature to technical debt. Nearly all products have some level of technical debt. Things that were learned by doing the work, things left undone in favor of getting something in front of stakeholders for faster feedback, or simply a lack of knowledge of better ways to do things. Since the technical debt is inherent in the product, I would suggest that inspection of the product is the best way to determine the level of technical debt and the impact of this technical debt on the work planned during Sprint Planning.


11:26 am February 19, 2020

What is the main reason for the latest product increment to be an entry?

Increments are cumulative. The planned increment must include all previous increments.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.