How are tasks handled by the development team when having different skills set ?

Last post 04:31 pm November 4, 2019 by Ian Mitchell
2 replies
10:37 pm November 3, 2019

Our team has a way of measuring how many points we can enter inside the sprint based on previous history points gained. We are a total of 12, but 7 are software developers, and the rest is distributed in QA, Infrastructure, DBA, and Scrum Master. 

My question is, Should tasks be specifically separated for those people inside the team even if they don't contribute to the sprint goal? because basically on sprint planning all tasks that are included from the backlog are the development of new features but meanwhile everyone else whose expertise is not programming is waiting to test a specific feature and doing others stuff like meetings and getting things done related to their daily activities which are not on tasks on board. which means the next spring we have more points gained if we meet the goal, which means more work for developers specifically.

Our formula takes into consideration that 12 people are working on the development which is true because in the development team everyone has something that contributes to meet the goal, but if all tasks on board are set for development of new features most pressure goes to developers.

Open to recommendations. 

Thanks in advance. 


02:50 pm November 4, 2019

Hi Jefri,

the developers should only estimate the work they are able to archive in my opinion. How they will estimate, it's a decision of the team itself.

Sounds like you have 4-5 people on which the team has to depend on. Dependencies are risks for the dev team and they should be mitigated.

Better build cross functional team(s) with the mandatory workers (maybe with the DBA) as member of the scrum team. Then try to organize the work with the vision the dev team can create releasable software. Maybe put QA in the DOD and DOR, give DB and Infrastructure rights to the Dev Team, etc. Ask your team what it is missing for that vision.

Hope that helps

Nils

 

 

 

 

 


04:31 pm November 4, 2019

Should tasks be specifically separated for those people inside the team even if they don't contribute to the sprint goal?

Isn't the Sprint Goal a coherence that causes the Development Team to work together rather than on separate initiatives?


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.