Road map planning

Last post 07:59 pm October 8, 2019 by Peter Dawson
6 replies
07:03 pm October 6, 2019

Hi team,

My product owner is planning road map for four months. He wants to calculate epic estimation based on personal hours becuase leadership wants it on hour basis. But we work on story points,not hours. Its not my role, but I want to help with a solution on this. I came up with few scenarios for calculation of points to hours. But not satisfied with myself on accuracy. Does anyone goes through this situation?


03:19 pm October 7, 2019

If you're truly doing relative sizing it doesn't seem to make sense to translate points to hours. You could potentially look at the average points done and estimate how many Sprints it may take the team to complete the 'as is' Product Backlog or particular features within the road map. 

The other thing I'm reading is that your Product Owner is not empowered and is asking the team to put a square peg in a round hole.

What information are the stakeholders looking to gather by linking hours of work to a 4 month roadmap?


04:06 pm October 7, 2019

@Tarak 

Agile concept has been used because, the complexity of the projects where requirements are complicated and keep on changing. 

Here the questions is, if requirements are clear and not going to change then why you would need to follow the Agile and you could easily use SDLC modal.

However if Agile is mandatory to be used then I think you can provide high level estimate based on your previous velocity points. 

Thanks

 


06:38 pm October 7, 2019

He wants to calculate epic estimation based on personal hours becuase leadership wants it on hour basis

Does he think that is a good reason?

Why is “leadership“ regarding how a Product Backlog is managed and estimated not entrusted to the PO, and team members such as yourself who have concerns over accuracy?


02:38 pm October 8, 2019

@Tony Divel: Leadership is looking for Personal Hours becuase Hours are directly have direct relation to costs but not with story points.

For leadership, Its all about two points, a. When the feature will deilver b. How many personal hours/days needed to finish this feature 


03:26 pm October 8, 2019

Is the PO or someone else able to reasonably come up with an average cost per Sprint for the Scrum Team? 

There ought to be a way to simplify the answer to those questions knowing that these are forecasts based on what is known at the time and are likely going to change due to the complex nature of the work. 


07:59 pm October 8, 2019

here's an  old link / disussion that might help 

 

https://www.scrum.org/forum/scrum-forum/8360/mapping-story-points-hours


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.