Hard to estimate and the first time implementations on sprint

Last post 05:55 am August 8, 2019 by ezgi kakaliçoğlu cihan
2 replies
06:54 am August 5, 2019

Hi,

 

We are new scrum team and we are making a new product which has become newly exist. So in planning meeting we commit the PBIs but we face so hard situations. As a result we can not finish all of our tasks. How can we deal with accomplishing the sprint? 

 

Thanks


05:46 pm August 5, 2019

Why not commit to an achievable Sprint Goal? The PBIs on the Sprint Backlog would be a forecast of the work needed. The team could inspect and adapt the forecast during the Sprint as more is learned.


05:55 am August 8, 2019

Hi Ian,

This is a good idea. I will discuss with the team and try this. Thanks a lot!


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.