Exam Question
If an inspector determines that one or more aspects of a process deviate outside acceptable limits, when must an adjustment be made?
- After Scrum Master approval
- After clarifying all the details with the Product Owner
- The deviations should be discussed at the Daily Scrum and then an adjustment must be made
- As soon as possible to minimize further deviation
I selected 2, after clarifying with the PO.
However, the answer is 'as soon as possible.' My understanding is that the PO decided on what needs to be changed; there maybe multiple stakeholders but direction comes from PO.
Your thoughts please.
This question came from the PSM1 exam prep
http://mlapshin.com/index.php/scrum-quizzes/sm-learning-mode/
Thank you
What does the Scrum Guide say about when adaptive adjustments ought to be made, the formal events which support it, and the associated responsibilities of team members?