Hello,
When different scrum teams are working on a single product, would the PO meeting the representatives from each team to compose the Sprint Goal and select items from the PB so that the representative can work with its team again to create their separate sprint backlog or all the team members converging at the same time to check the PB so that they can co-ordinate dependencies and create their SB would be a better option for Nexus Sprint planning?
Thanks.
From your reading of the Nexus Guide, might it be possible to do both?
From actual practice in my nexus getting all the team into the sprint planning has helped teams to co-ordinate better and sort out depedencies , it will also help to reduce the handoff of the teams representative again discussing with their teams to create their sprint backlog .