Last post 01:02 pm May 28, 2018 by Chris Belknap
5 replies
03:30 pm May 24, 2018

What is the best practice attitude for Scrum Master or Development Team, if Product Owner change the scope of User Story or enlarge the Test Cases during Sprint Execution ? 


04:15 pm May 24, 2018

The Scrum Guide says “Only the Development Team can change its Sprint Backlog during a Sprint.”

Do the user stories and test cases you refer to constitute work which has been planned into the Sprint Backlog?


04:26 pm May 24, 2018

And, if the user stories need to change because the Sprint Goal becomes obsolete, the Product Owner should consider cancelling the Sprint.  Then those user stories should be discussed in the next Sprint Planning.


08:29 am May 25, 2018

User stories or acceptance criteria should not be changed and as a scrum master you should not allow this to happen.

There must be an escalation matrix your org must be following.


12:36 pm May 28, 2018

Hi All,

 

Appreciate for your feedbacks.. I am also agree on that Acceptance Criteria can not be enlarge and User Story scope can be change


01:02 pm May 28, 2018

>> There must be an escalation matrix your org must be following.

How might something like an escalation matrix detract from self organization?  Shouldn't a self organized team be able to work through this themselves?


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.