Where to add tasks which cannot be linked to a sprint backlog item

Last post 08:03 pm November 1, 2017 by Ian Mitchell
1 reply
02:32 pm November 1, 2017

Where do you add tasks which cannot be linked to a specific backlog item which is in scope of the sprint. I mean tasks like demo preperation, create release with configuration files, regression test etc.


08:03 pm November 1, 2017

Why not just plan them into the Sprint Backlog as part of the forecast of work? There’s no reason to assume a Sprint Backlog must be decomposed hierarchically into items and constituent tasks.

Are you using a tool of some kind, and its design characteristics are shaping your thinking?


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.