Estimation in sprint

Last post 06:51 am September 12, 2017 by azhar osman
11 replies
08:29 am August 28, 2017

It is said that product backlog should be estimated in grooming meeting, also teams perform estimations at task level in the how part of sprint planning meeting.

I just need clarification when estimations should be done ( sprint estimations) ?

As per my understanding, in backlog grooming we do not split the PBI at task level so task level estimations cannot be done at that time. A PBI is divided into technical tasks in planning meeting and detailed task level estimations can be done only in planning meeting ( how part )

I need experts opinion on this please....

 

 


08:39 pm August 28, 2017

Are you talking about the estimation of work on the Product Backlog or the Sprint Backlog?


08:59 am September 5, 2017

Ian Mitchall,

I am talking about the estimation on both Product Backlog Items and Sprint Backlog.

 

Thanks.


08:09 pm September 5, 2017

What does the Scrum Guide have to say about "the act of adding detail, estimates, and order to items in the Product Backlog", and what sort of process that act is?

What does the Guide have to say about "estimated effort" in the Sprint Backlog and the event in which such work is planned? What does it say about when "estimated remaining work is updated"?


10:33 am September 6, 2017

Ian,

As per scrum guide, adding details, estimates and ordering of items is done mainly in backlog refinement or backlog grooming meeting.

And estimated effort is updated as work is performed or completed in a sprint.

But I need clarification on estimates during backlog grooming and the estimates done during sprint planning?

If a backlog item is estimated in grooming meeting, should it be estimated again in sprint planning meeting  ( how part) ?

I think estimation at backlog grooming level is very high level , although details are added in user story/backlog item but it is not divided at task level. A PBI is divided at task level in planning meeting and then possibly good/accurate estimates can be done.

 

So an estimated PBI at refiment/grooming meeting will be re-estimated in planning meeting ( after adding tasks to it ) ?

Thanks....

 

 

 


03:28 pm September 6, 2017

Is there any reason not to keep estimates up to date, where they are thought to be inaccurate, so the best possible forecast of work can made at the necessary time?


06:55 pm September 6, 2017

Even though the team may estimate an item prior to Sprint Planning, the option should always be available for the team to revisit an estimate and change it if more information is learned or made available that can affect the size of the item.  

A PBI's estimate should be available for modification all the way until the item is offered and forecast during Sprint Planning.


12:04 am September 7, 2017

We estimate the user stories in story points during backlog refinement meetings.. and do revisit those once more during the Sprint planning to make sure it's still correct based on current understanding and if it requires changes, we update it based on inputs from the team members. The task level estimation are in hours and not in story points and is done during 2nd part of the Sprint planning and not during backlog refinement meetings.


12:35 pm September 11, 2017

Ian," Is there any reason not to keep estimates up to date ", yes there is no reason not to keep estimations up to date. But estimation at planning meeting is not optional I think. We have to do task level estimations in how part of sprint planning meeting as explained by Debashis Mishra. So can we conclude that a PBI must me estimated in detail ( task level) in sprint planning ( how part ) and we cannot rely on the estimation done in grooming meeting.


04:01 pm September 11, 2017

Azhar, I will acknowledge that I find little if any value in task estimation, but your last statement sticks out to me:

 

we cannot rely on the estimation done in grooming meeting

 

What reason(s) might you have to conclude that previous PBI relative estimation is unreliable?   Keep in mind that from a Lean perspective, we should not be doing anything that does not provide value (waste).


05:02 pm September 11, 2017

So can we conclude that a PBI must me estimated in detail ( task level) in sprint planning ( how part ) and we cannot rely on the estimation done in grooming meeting.

No. What you have described is only one possible implementation, even though it is certainly a very common one. However, a team might reasonably choose to do no further estimation at all when they address the second topic of Sprint Planning.

For example, the Guide says that work is decomposed "often to units of one day or less". That process of decomposition into the said units may be sufficient, during the Sprint, for the team to understand how much work remains on their Sprint Backlog at any given time.

Remember that Scrum does not mandate the formulation of tasks, still less task-level estimation. The important thing is that the team forecasts a selection of PBI's for meeting an agreed Sprint Goal, and has a plan for achieving it which can keep track of how much work is thought to be left.

The totality of that forecast of work must be achievable. Understanding the totality may require no more estimation than that of the associated Product Backlog Items during Product Backlog refinement.


06:51 am September 12, 2017

Timothy Baffa, my statement " we cannot rely on the estimation done in grooming meeting " was in fact a question. I needed answer to this and Ian explained it very well.

Thanks Ian for your kind explanation.

 

 


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.