How to prepare report after daily stand up?

Last post 01:12 pm August 10, 2017 by Timothy Baffa
2 replies
12:18 pm August 9, 2017

After daily standup, I would like to get following info -

 

1> For today, Issues going to be worked on by Dev along with estimates.

2> Time logged by Dev on previous date

3> Issues our team are facing to complete the task as estimated, if we are not on track

4> What difference are we making on the product, besides just working on assigned issues.

 

My project manager wants these reports.


08:18 pm August 9, 2017

From your reading of the Scrum Guide, how reasonable is it for a "project manager" to expect these or any other reports? 


01:12 pm August 10, 2017

Nikhil, assuming that your role on the Scrum Team is as the Scrum Master, you should know that the Daily Scrum is a Development Team-based meeting strictly for their benefit to align their daily work towards the Sprint Goal and discuss any issues that may impede them from reaching that goal.  

 

As a Scrum Master, your responsibility is to make sure that the team has the Daily Scrum, that their discussions are productive, and that they keep the meeting within the 15-minute time box.   That is it.

 

Also, it is critical for you to not only protect the team from any interference from outside, but to educate those (such as your "Project Manager") who are attempting to distort the purpose of the Daily Scrum or your role in it.

 

I urge you to read the Scrum Guide section on the Daily Scrum.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.