Skip to main content

Duration of Sprint

Last post 05:03 pm August 21, 2017 by Ian Mitchell
6 replies
10:47 am August 9, 2017

Hi everybody,

I am currently preparing the PSPO exam and have a question : Scrum guide usually talk about 1 month sprint duration but I understand it can be shorter. So my question is : is it the PO who select the lengh of the sprint or is it a common decision discussed in the scrum team ? I assume the lengh is selected during the sprint planning, true ?

Thanks for your help,

Clemence


08:11 pm August 9, 2017

Don't you think that the optimum length of a Sprint should also take into account technical constraints visible to the Development Team? Also, might consistency in Sprint length be useful? 


10:38 pm August 9, 2017

The Scrum Guide says:

Once a Sprint begins, its duration is fixed and cannot be shortened or lengthened.

So given that Sprint Planning takes place after the Sprint has begun, when might be an appropriate time to decide on a change, if you find your Sprint length isn't sufficient?


11:52 am August 10, 2017

Hi,

Thanks for your feedback, it is more clear now !

Best Regards


02:42 am August 16, 2017

So given that Sprint Planning takes place after the Sprint has begun, when might be an appropriate time to decide on a change, if you find your Sprint length isn't sufficient?

I'd look at this the other way around. First define your time box, then identify what can be done within that time box. Sprint planning allows the team to discuss what is possible within that time and how to bundle that up into a common goal.

The complexity comes from things like technical constraints. As an extreme case, if I know it will take at least a day to create a releasable product, then a 1 day sprint would be a mistake.

Also, you'll want to ensure that you have enough time to successfully meet a goal that adds value. To do this I'd want sprints long enough that we can complete multiple PBIs and still have some slack.

All of this means that soliciting input from the entire scrum team to adds a lot of value, even if your time box is defined before the actually planning starts. If the time box needs to be adjusted, I'd usually do that as an action item from the retrospective.


02:12 pm August 19, 2017

Hi, 

I have a query here. "Once a Sprint begins, its duration is fixed and cannot be shortened or lengthened". On other hand we read  "A new Sprint starts immediately after the conclusion of the previous sprint. What if in the previous sprint all tasks finish before time. in this scenario, Does that particular development team wait or they can add additional tasks to it after consulting the product owner since adding tasks will impact 1) prioritized product backlog & 2) sprint goal which can not change during a particular sprint. 


05:03 pm August 21, 2017

They can do whatever they want or think best with the remaining time, as long as the Sprint Goal has been met and will not be subsequently compromised.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.