Let's say you have a team of 7 developers. In Sprint X, 5 of them work towards the Sprint goal (defined by the PO), but 2 of them work in items that are not part of the Sprint goal, but need to be done (e.g. configuration changes etc.) during that Sprint. The 5 developers deliver towards the Sprint goal, but 1 of the other 2 developers don't finish their work assigned. How do you handle that unfinished work in that situation?

 

 


09:35 am September 23, 2024

How do you handle that unfinished work in that situation?

Any unfinished work should be reprioritized and added to the product backlog. In the sprint retrospective it is important to understand why this work could not be completed (you should have got an idea about it during the daily scrum). Then during the backlog refinement or sprint planning, take a call if this is to be done in the next sprint or deprioritized 


11:38 am September 23, 2024

but 2 of them work in items that are not part of the Sprint goal, but need to be done (e.g. configuration changes etc.) during that Sprint

If those things needed to be done during that Sprint, why weren't they a commitment for this team, or for another one?


08:07 pm September 25, 2024

but 1 of the other 2 developers don't finish their work assigned.

Scrum strongly encourages self-managing teams. The team should decide how much they can take on and complete. The wording 'work assigned' raises alarm bells.

The team takes responsibility for the work and also for any unfinished tasks,not individuals. Why don't other team members step in to help with the configuration work? From the description, it seems there is not a Scrum team, but rather developers grouped together."

 


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.