Hi there! Does anybody has a test to measure the level of scrum implementation in a team?
I'm kind of struggling in getting an artifact to help me measure the level of scrum implementation in my team.
Does anyone has a test or any artifact that can share with me in order to solve my problem?
Thank you in advance for your cooperation.
In Scrum, that artifact would be the Increment. Can your team plan and build a Done increment of immediately usable quality within a Sprint timescale? That's the acid test of a good Scrum implementation.
Agree with @Ian. I will also say that the stakeholder's responses and desire to use the Product can be a pretty good indicator also.
Why would you want to "measure the level of scrum implementation in my team"? What do you think is measurable? And what would this "measure" be used for? Sounds like a Key Performance Indicator trying to happen. If that is the case, try reading Evidence-Based Management Guide that is available on this site and see if that sparks any ideas.