Cost and Resource Estimation

Last post 06:55 pm November 25, 2018 by Renato Alves dos Santos
7 replies
02:17 pm January 16, 2017

Dear All,

What is the best method to estimate cost and resources for an Agile Projects?.

In traditional method where we have a big picture and needed list of tasks to be done so , based on we can conclude the required resource and estimate cost based on timeline.

how to handle project with fixed timeline using agile method ?.

Thanks
Senthil


02:23 pm January 16, 2017

How does having a fixed timeline work with your organisation's adoption of Agile?

If a Scrum Team has 8 members (including PO and SM), can you not calculate the cost using 8 x the amount each member is paid per day x number of days in the Sprint to give you an idea of how much per Sprint? Then the organisation can decide what features are worth spending that amount per Sprint are in some order of value.


03:07 pm January 16, 2017

Thank you Alex.

How can i calculate required resources and time at the time of proposal ?.

In some cases client want to complete project with in 3 months time.. is it good to adapt Agile or waterfall method?

Thanks
Senthil


04:42 pm January 16, 2017


Posted By Senthilkumar Muthusamy on 16 Jan 2017 03:07 PM

In some cases client want to complete project with in 3 months time.. is it good to adapt Agile or waterfall method?



Ask what they mean by 'complete a project'? How can they be sure there will be no changes to business needs, technology, etc.? Why would they want to be so sure?


12:08 pm January 18, 2017

Ask what they mean by 'complete a project'? How can they be sure there will be no changes to business needs, technology, etc.? Why would they want to be so sure?




How can we take a call , when client wants us to complete the entire project within 4 to 6 months of time. so adapting waterfall will be a good option ? or proceeding with multiple scrum team to meet the project deadline.


02:43 pm January 18, 2017

Does anyone actually want this to be run as an agile initiative, and if so, why? From what you say, it doesn't sound like there's much of an appetite for incremental risk mitigation and delivery.


12:02 am November 24, 2018

Imagine the following scenario, where the client is searching for a company to work in a certain project that it expects to last like 5 years, and shows a fixed budget they can pay for it. How to measure if this amount of time is enough to conclude the project? and how to know if the money offered is enough to the project company to make profit of it? Usually the customers put it in to the market and ask the project companies to estimate their sales costs, and one of the criteria, the client take to account when it's deciding which company to hire, is the project companies's sales cost.  How to calculate it, as soon as it'll be necessary to have this info before the company even decides they'll provide the service?

 

"In traditional method where we have a big picture and needed list of tasks to be done so , based on we can conclude the required resource and estimate cost based on timeline."


03:59 pm November 24, 2018

I was reading a very good topic about ways of selling Agile through Target-Cost Contracts. I'm sharing it bellow:

http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.93.6734&rep=re…


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.