Difference between "produced" and "done"?
Hi,
I think I got the difference, but it always better to have a check.
At the end of every sprint, a increment or Integrated Increment has to be produced. The Scrum or Nexus Integration Team is accountable for it.
The PO says if the produced increment is "done" or not.
Am I right?
Tks,
Stéphane.
It's the Definition of Done which determines whether an increment is "done" or not.
In other words, "done" isn't something that the Product Owner just happens to decide. The DoD has to be agreed with the Development Team, and no later than the Sprint Planning session for the Sprint to which the Definition is to be applied.
Tks for the clear answer!