Scaling Agile Development
Hello,
Based on my knowledge, when multiple teams are working on a product, they should define the definition of "Done" that makes their collective work potentially releasable.
Is there a meeting that the Scrum teams collect their work together before displaying it in the Sprint Review?
Thanks all!
If any integration tasks remain outstanding, no matter how trivial, then an increment is not "Done".
Integration matters - including the collation of work for review - should therefore be planned into each team's Sprint Backlog. This may take the form of a joint meeting or it could be tasks to be collaboratively performed.