Skip to main content

Why is the Sprint duration fixed but the duration of the other events not?

Last post 11:35 am April 28, 2021 by Scott Anthony Keatinge
5 replies
08:58 pm May 27, 2020

Hello everyone,

Respect this part of the Scrum guide I have some question:

"Once a Sprint begins, its duration is fixed and cannot be shortened or lengthened. The remaining events may end whenever the purpose of the event is achieved, ensuring an appropriate amount of time is spent without allowing waste in the process."



In a unfrecuency Sprint:

- If the Sprint Goal and the searched increment is achieved before the end date of that Sprint, why couldn't I short the sprint?

- Why the rest of the other events can finish if they achieve their purpose but not the Sprint event?

 

Thank you!

 


03:31 pm May 28, 2020

The Sprint is fixed in duration in order to help a team establish a cadence.  If the duration of the sprint is constantly changing, the ability to consistently forecast a body of work to deliver a potentially releasable increment becomes difficult if not impossible.  Do you plan for 2 weeks, 2 days?  Or do you just decide to build something and take as long as it takes? 

If you are finding that you are consistently achieving your Sprint Goal early in the Sprint, could it be that you are able to include more work on a consistent basis? 



The other events do not need a specific cadence other than their occurance. Each event is for a specific purpose but only one of the events, the Sprint, has the purpose to produce an increment of value. All of the other events are used to prepare work or to gain feedback based on the work that has been done.

 


05:08 pm May 28, 2020

- If the Sprint Goal and the searched increment is achieved before the end date of that Sprint, why couldn't I short the sprint?

- Why the rest of the other events can finish if they achieve their purpose but not the Sprint event?

The Sprint is the time-box for meeting the Sprint Goal. If it were to be shortened, what effect might there then be on predictability and transparency?


03:29 am April 27, 2021

Two things to consider here:

  1. When you do Sprint planning, it is very helpful to have any idea of your team’s velocity. If Sprint durations keep changing, velocity becomes a much more complicated calculation
  2. If you shorten your Sprint, it would probably mean have to reschedule your Review, Retrospective and next Sprint Planning. The best practice to aim for consistency with the timings of Scrum Events.

However, according to the Scrum Guide, you can re-negotiate the Sprint scope as long as it does not endanger the Sprint Goal.

We normally chuck in a few additional Stories mid-Sprint, if the team are excelling themselves.


08:32 am April 28, 2021

Hello,

Q: If the Sprint Goal and the searched increment is achieved before the end date of that Sprint, why couldn't I short the sprint?

Ans: In the Scrum framework, to maintain cadence with all the stakeholders we are working in a fixed-length sprint with a timebox. So, you can get consistent potential increments at the end of each sprint.

Let's discuss one example: assume that there is a two-week sprint so the client knows that on day 14th I've to schedule my calendar for the sprint review meeting. now, you are saying that what if I have completed work on day 10th. Now, Is it good to send mail to a client for informing them that you have completed the sprint earlier? or just think that what the client will think if this type of scenario will occur frequently?



So, if you are new in scrum then you will get some time to maintain velocity. once your velocity would be stable, the team can estimate easily sprint backlog. and if work completed earlier, the team can discuss with PO and can take more adhoc requirements into Sprint Backlog based on priority. 

  


11:35 am April 28, 2021

If you have a done increment on the 10th, the PO & Developers can see if there are any other items in the PB that would meet the sprint goal or if there are any improvement PBIs that could be worked on that were created during the last sprint retrospective. 

Remember, the scrum team is accountable for creating a done usable increment at least once a sprint, which means that there isnt anything stopping them from creating multiple increments per sprint. 


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.