Sprint review opportunity
I'm practicing with some test and i don't understand why b) and c) responses are wrong.
The sprint review is an opportunity to review
a) Timeline y budget
b) Defects and causes
c) Requirements and Capacity
d) All of the above
Correct answer is a).
Tks
I'm practicing with some test
What test, and why do you have confidence in it?
It belongs to the book "Srcum Narrative and PSM Exam Guide"
If you read the Scrum Guide section that describes the Sprint Review (https://scrumguides.org/scrum-guide.html#events-review) how do you feel about the answer from that test? Personally, it makes me question the validity of the messages in the book because I don't believe that A) or C) would be part of the discussions. Timelines and requirements might be partially discussed but not budgets and capacity. The entire question seems suspect to me.