Skip to main content

Adding avery important item to Sprint

Last post 09:58 pm November 16, 2019 by Saeed Rahimi
6 replies
12:30 am November 15, 2019

The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress. What should the Development Team do?

Correct answer : Inform the Product Owner so he/she can work with the CEO.

and what happens if its not CEO but the PO itself ?

03:13 pm November 15, 2019
what happens if its not CEO but the PO itself ?

Does this addition of item impacts the Sprint Goal ? Does the PO aware about the consequences of adding it ? 


03:47 pm November 15, 2019

The reason PO and Dev Team work together is due to the Scrum Values.

  • People personally commit to achieving the goals of the Scrum Team.
  • The Scrum Team members have courage to do the right thing and work on tough problems.
  • Everyone focuses on the work of the Sprint and the goals of the Scrum Team.
  • The Scrum Team and its stakeholders agree to be open about all the work and the challenges with performing the work.
  • Scrum Team members respect each other to be capable, independent people.

If the PO has determined that the current Sprint Goal is no longer valid, cancel the Sprint and start a new one immediately. What's the point in finishing unwanted work? Otherwise, the PO and Dev Team's motivation to alter the Sprint Backlog resides in their ability to live the values. So they gotta work together and have the courage to do the right thing.


04:26 pm November 15, 2019

The reason why this answer is correct is because it is up to the PO to make the final decision about the order of PBIs. If it is the PO itself, then Dev Team and PO collaborate about this situation, due to Dev Teams' ownership of Sprint Backlog, PO can not just throw new things in on its own.



Of course, PO can cancel the sprint if Sprint Goal is no longer valid, but what if it still is valid? There is a reason why as a team we commit to the Sprint Goal, but only forecast scope of the Sprint and explicit only that to not make changes that would endanger the Sprint Goal.


07:43 pm November 15, 2019

The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress. What should the Development Team do?

In Scrum/Agile, work is never "pushed" to the Development Team.   Once the sprint starts, no one has the authority to make the Development Team work on items outside of their forecast.

From the Scrum Guide:

The Sprint Backlog... belongs solely to the Development Team.

No one can force the Development Team to work from a different set of requirements (than those identified from the Product Backlog).

Often when such a situation arises, there is a collaborative discussion between the PO and Dev Team around the value and urgency of the item.   There does not need to be a reason or fear of such a topic becoming contentious.

Ultimately though, it is solely up to the Development Team to decide if they wish to accept such a late-arriving item, regardless of it's critical-ness, and provided that it does not endanger the Sprint Goal.

 

 


08:34 pm November 15, 2019
and what happens if its not CEO but the PO itself ?

Wouldn’t a good Product Owner seek the opinion of the Development Team before deciding what is important that Sprint?


09:58 pm November 16, 2019

Thank you all for your thoughts


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.