Scenario- " Team A=8 members, and one more team member from SRE contributing user stories to Team A. Should the SRE user stories be estimated or zero pointed? Zero pointed now because Team A feels that member might not take their work and any issue that member contribution is low and SRE user stories are primary focus for the SRE team member. In case SRE Team member does'nt complete user stories in sprint then the the Team A's burndown metric might get impacted.

So is it ok to have SRE user stories be zero pointed?


03:11 pm October 23, 2019

Can they be zero pointed? - Yes, they can be. But can you think of the reason why you point stories in the first place?

From the scenario you describe, it doesn't appear the true purpose is served and it also appears that there is a disconnect in being a team. It appears that one team is only concerned about their burn-down and doesn't treat the other as part of the team. So that begs the question why even enter such a setup?


04:16 pm October 23, 2019

So is it ok to have SRE user stories be zero pointed?

Would that solve a problem, or hide it from view?


08:24 pm October 23, 2019

Why is the Development Team being encouraged to silo work individually within the team?   

How does such a practice promote team-based ownership and responsibility for the entire sprint forecast?   


08:40 pm October 23, 2019

A story point is a  a relative unit of measure, decided upon and used by individual Scrum teams, to provide estimates of effort for completing a requirement. 

So if a User story is zero, then is there zero effort  to complete that requirement ??

From what I am reading and understanding, its more about dividing the works items. Overall the dev team is responsible for the entire sprint goal. 


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.