Hard to estimate and the first time implementations on sprint
Hi,
We are new scrum team and we are making a new product which has become newly exist. So in planning meeting we commit the PBIs but we face so hard situations. As a result we can not finish all of our tasks. How can we deal with accomplishing the sprint?
Thanks
Why not commit to an achievable Sprint Goal? The PBIs on the Sprint Backlog would be a forecast of the work needed. The team could inspect and adapt the forecast during the Sprint as more is learned.
Hi Ian,
This is a good idea. I will discuss with the team and try this. Thanks a lot!