Skip to main content

What happened if a critical component cannot complete within a Sprint

Last post 11:09 pm August 6, 2019 by Alex C
6 replies
12:14 am August 3, 2019

Hi all,

 Would like to understand what would the others do in the event that one of the member told you (as product owner) that he couldn't complete his task during the end of the sprint.

Assuming that his task is a critical for the subsequent sprint and he has been reporting the progress is stayed on track during the standup meetings

Thank you.


04:34 pm August 3, 2019

A couple of things stand out in the situation that you describe. Why is a single individual responsible for tasks, or where is the team commitment to the Sprint Goal? Why does the team (or at least this one individual) not have the courage to be able to accurately state when work is at risk of not being completed and ask for appropriate help?

Those are questions to examine at the Sprint Retrospective, but doing so are critically important.

But we also have a here and now. As a Product Owner, you should engage the Scrum Master on the concerns. You can also start to work on reordering the backlog and managing stakeholder expectations. The best things that you can do, in a Product Owner role, is to make the current state of the Product Backlog visible and transparent and to be sure to maximize the value of the Development Team for the next Sprints.


05:01 pm August 3, 2019

Why was he “reporting” progress at all, given there was an emergent body of work that presented risk? Weren’t you collaborating as a Scrum Team during the Sprint, so that progress would be transparent, and you could inspect and adapt accordingly?


01:40 pm August 4, 2019

Thank you Thomas and Ian for the response. Both of you have raised valid points. 

However, I couldn't able to answer the questions as the example that I raised is not a real-life situation. There would be a number of suggested reasons arise to such situation, e.g. inexperience of the team, product owner or scrummaster etc. which I probably won't talk about it. 

But, in the event that thing do happen, what will be the best course of actions for the product owner or the team? Should the sprint be extended since this is a critical component? On the other hand, I understand that it is not advised to extend the sprint under normal scenarios.

Cheers!

 

 

 

 


06:47 pm August 5, 2019

On the other hand, I understand that it is not advised to extend the sprint under normal scenarios.

It is never advisable to extend the length of an active sprint at any point in time.   To do so is a direct violation of the sprint time box.   The only acceptable point in time to adjust the sprint length is at the conclusion of a sprint, before the next sprint begins.

To put it another way, would you move a bullseye target to improve the accuracy of an arrow you just shot?


10:05 pm August 5, 2019

But, in the event that thing do happen, what will be the best course of actions for the product owner or the team?

My answer to that question is that Thomas, Ian and Timothy have already answered it. This isn't an individual's issue. It is an issue for the entire Scrum Team if this situation comes to fruition and isn't made apparent until the end of the Sprint. There should be constant communication among the team, especially when something endangers the items needed to satisfy the Sprint Goal.  If this happens, it should be the first, and possibly the only, item that is discussed in the Retrospective for that Sprint.  And it should be a continuing discussion among the Scrum Team as you progress going forward so that it is avoided in the future. 


11:09 pm August 6, 2019

Hi Daniel and Timothy, 

Thank you for your responses. I totally agreed with both of you. The best course of action is to let the scrum team to decide and learn to avoid such issue occurs in the future.

Cheers!!

 

 

 


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.