Skip to main content

How to split User stories?

Last post 01:30 am March 6, 2018 by Beenish Zaidi
6 replies
06:20 am February 23, 2018

Hi All,

This is my first post on this forum. Hoping to find answers to my questions and would definitely try to pitch in wherever possible.

I have had an exposure in scrum projects however this is the first time I am working as a SCRUM MASTER for a fairly new project. The team consists of 2 full-time developers and 1 tester along with a dev lead who just manages the entire dev team. None of them knows how a scrum team works. So basically, I have been asked to get this project running in a scrum fashion as much as possible.

We have a 2 week sprint (10 business working days). The developers have been given the first 7 days to complete their coding and last 3 days are meant for pure testing. Any thoughts on this approach?

 

Question:- How to split the user stories?

To give you all a basic idea, we have to create a new form wherein 9 fields need to be added with few of them having minor validation. Since this was sprint1, we went ahead with 9 stories, that dealt with one story per each field. The developers created a UI, added all the 9 fields and later released it for testing on the 8th day. Both the devs and tester said that even if they would have released the story for testing as n when one field is being created and placed on the form, the tester would still have to test everything, every time and that would have been time-consuming. I am not sure how to deal with this scenario. Is it valid what they are saying? or I could club this into 1 story and would have created 9 sub-tasks for the developers for every field.

The current approach also hampers my sprint burndown chart since we see a dip only on the 7th day.

 

Please suggest.

 

Thanks !!

 

 


07:29 pm February 23, 2018

We have a 2 week sprint (10 business working days). The developers have been given the first 7 days to complete their coding and last 3 days are meant for pure testing. Any thoughts on this approach?

Who is giving them this time? There are two weeks. Isn't it up to the Development Team to decide how to best to use that time so the agreed Sprint Goal can be met, and a Done increment delivered?

Both the devs and tester said that even if they would have released the story for testing as n when one field is being created and placed on the form, the tester would still have to test everything, every time and that would have been time-consuming

What errors may be caught by doing that testing, and what assumptions might be challenged? How might the process be automated? Might there be an advantage in designing an automated test first, before developers even attempt to satisfy that requirement?


10:27 am March 1, 2018

Doing all the dev first and then doing the testing last feels very mini-waterfall and will hurt you sooner or later..  

What happens if you don't complete the testing in time?  You have nothing 'done'.  It's far better to have 5 things done and releasable than 10 things 'nearly done'.

Think about limiting your work in progress and focus on getting dev AND test completed one story (or as few as practical) at a time.  Remember the 'I' in INVEST.  If the story is independent, it will stand up up under it's own weight and is something useful that could be released on its own.


01:18 pm March 1, 2018

Both the devs and tester said that even if they would have released the story for testing as n when one field is being created and placed on the form, the tester would still have to test everything, every time and that would have been time-consuming

And that's where you introduce testing automation. Yep, gotta be thoroughly tested, no argument there, however if you are continuously integrating AND your testers are working in parallel with developers on automating their routine tests, that's what makes it tick, that's what makes value flowing from the Dev Ready to the Done column.


04:54 pm March 1, 2018

Depending on what each field did, the tester could have easily tested the specific field and then run integrated testing when the entire form was completed. For example, fields require very specific text to be allowed, the tester can easily test that functionality on the specific field without having the entire form completed. If there is a special character, for instance, that was allowed to be entered but should have been blocked; the tester would have found that early and the dev team could have fixed this bug prior to full testing of the entire form. 

Automated testing is definitely the way to go for this but until then, if it is at all possible to test pieces of a whole; it is beneficial. Otherwise, your tester is providing no value to the team until the last few days of the sprint. 

Your question regarding should this have been a single user story with 9 tasks, versus a single user story really depends on what the form is and what the fields do. If you're creating a customer entry form when the 9 fields are basic data input; I would place this as a single user story. If you're creating a form that contains 9 separate fields that each perform a specific action, I would be more inclined to create a user story for each. Others may have a different idea on this though.


06:39 pm March 4, 2018

Hello Aarti,

 

I would like to propose an exercise to you (+ your PO and best case the whole team) about splitting User Stories -->  

it is called "Elephant Carpaccio" http://alistair.cockburn.us/Elephant+Carpaccio+Exercise.

 

I learned a lot when I did it myself and I conducted it several times with differen teams. 

 

Cheers

Joerg

 


01:30 am March 6, 2018

Hi Aarti,

What's the reason of creating one story per field? It's very important to cut waste. Story should be based on an INVEST principle. One field and it's validation per story does not seem smart use of INVEST principle. I will advice to go through Joerg Karlinger approach and see how it helps you. Thanks.


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.