Mistake in scrum guide?
The Guide says:
The sprint Goal is an objective set for the Sprint that can be met through the implementation of Product Backlog.
Should be:
The sprint Goal is an objective set for the Sprint that can be met through the implementation of selected for the Sprint Product Backlog Items.
Cheers,
Romek
Romek,
I had to do a text search on the Scrum Guide to find your quote. (Found it on page 9, Topic One, paragraph 3: What can be done this Sprint?)
I agree the text suggests that a sprint goal is to be met by implementing the ENTIRE Product Backlog.
I would like to suggest the following text:
The Sprint Goal is an objective that will be met within the Sprint through the implementation of **selected** Product Backlog **items**.
There is no such thing as implementing the entire product backlog. Product backlog is evolving as long as the product exists.
Hello Christiaan,
Thanks for your answer. Yes that is the quote. I was writing about.
Your suggestion is fine I believe, I wanted to put more emphasis on the fact of misleading wording in Scrum Guide.
Seems that most people do not read it in detail or presume that it is not really intended.
Cheers,
Romek