I am new to Scrum.I have few doubts.

Last post 09:17 am September 23, 2014 by Melanie Prescott
3 replies
Anonymous
06:01 pm September 8, 2014

who will cancel the scrum and How to cancel a scrum?


09:37 am September 9, 2014

Why do you want to cancel a Daily Scrum ?


09:57 am September 9, 2014

Maybe you mean cancel a Sprint?
Only the Product Owner can cancel a Sprint. He will do so if the Sprint goal does not make sense any more.
All done PBIs are reviewed. All undone PBIs go back to the Product Backlog and the team continues with a new Planning for the next sprint.


09:17 am September 23, 2014

I don't really understand the question? And also - if you have doubts, are you talking about not using scrum at all?


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.