I was just going through the scrum guide and under the sub section Topic Two: How will the chosen work get done? i read the below statement 

Work planned for the first days of the Sprint by the Development Team is decomposed by the end of this meeting, often to units of one day or less.

Does it mean that work that will be done at the start of sprint will be discussed at the end of sprint planning? Or what exactly it refers to?


09:04 pm April 4, 2017

It just means that before the sprint planning is finished the Development Team will have the work for the first days of sprints decomposed to smaller bits - usually one day or less.

They don't have to do this for all the elements taken to the sprint. Elements for later part of the sprint can be decomposed later. So at the end of the meeting team should have some strict vision, plan for the first days reflected by set of really small tasks and some rough vision how other elements will be delivered and how they will achieve the sprint goal.

Why? Because "the Development Team should be able to explain to the Product Owner and Scrum Master how it intends to work as a self-organizing team to accomplish the Sprint Goal and create the anticipated Increment.".


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.