Can PO delegate the writing of user stories ?

Last post 08:33 am December 23, 2022 by Abayomi Joseph Ajayi
2 replies
04:05 pm December 21, 2022

I am working as Scrum Master for a cross-functional team including Business Analyst, Developers, Embedded Testers and a Product Owner.

I understand that the Product Owner is accountable for the Product Backlog Items.

My question is can he/she delegate the user story writing to the team which could then be further reviewed & refined during Backlog Refinement or even during Sprint Planning (if required) by the entire team.

Thank you.


07:04 pm December 21, 2022

The Scrum Guide says:

The Product Owner is also accountable for effective Product Backlog management, which includes:

  • Developing and explicitly communicating the Product Goal;

  • Creating and clearly communicating Product Backlog items;

  • Ordering Product Backlog items; and,

  • Ensuring that the Product Backlog is transparent, visible and understood.

The Product Owner may do the above work or may delegate the responsibility to others. Regardless, the Product Owner remains accountable.

User stories are an example of how Product Backlog items might be expressed, and which would be subject to further ongoing Product Backlog refinement.

If the creation of such items was left until Sprint Planning, you might wonder how the work could possibly be ready for consideration in that event.

 

 


08:33 am December 23, 2022

My question is can he/she delegate the user story writing to the team which could then be further reviewed & refined during Backlog Refinement or "even during Sprint Planning (if required)" by the entire team.

Absolutely just as Ian has said and as per the Scrum Guide, the Product Owner can delegate "responsibilities" to the Developers and the Scrum Master however, he is still accountable for the PBL.

"even during Sprint Planning (if required)"

By the time the Sprint Planning is initiated the PBL would have been ordered for the Developers to select the PBI for the Sprint. Product Backlog grooming/refinement is the act of breaking down and further defining Product Backlog items into smaller, more precise items, this is not done during the Sprint Planning (SP). This is an ongoing activity of the PO outside the dedicated SP. 

@Shailiesh by the way, Ian is well experienced, a great coach, you have to get used to his coaching technique if you are new on this forum. 

 


By posting on our forums you are agreeing to our Terms of Use.

Please note that the first and last name from your Scrum.org member profile will be displayed next to any topic or comment you post on the forums. For privacy concerns, we cannot allow you to post email addresses. All user-submitted content on our Forums may be subject to deletion if it is found to be in violation of our Terms of Use. Scrum.org does not endorse user-submitted content or the content of links to any third-party websites.

Terms of Use

Scrum.org may, at its discretion, remove any post that it deems unsuitable for these forums. Unsuitable post content includes, but is not limited to, Scrum.org Professional-level assessment questions and answers, profanity, insults, racism or sexually explicit content. Using our forum as a platform for the marketing and solicitation of products or services is also prohibited. Forum members who post content deemed unsuitable by Scrum.org may have their access revoked at any time, without warning. Scrum.org may, but is not obliged to, monitor submissions.